Validate Scope vs Control Scope

Key Differences and Importance of Validate Scope vs Control Scope in Project Management.

Introduction

In project management, scope management plays a vital role in ensuring successful project completion. It involves defining, controlling, and validating the project scope to meet the project’s objectives. Two essential processes within scope management are Validate Scope and Control Scope. While they may sound similar, they serve distinct purposes and have unique activities associated with them. This article aims to explore the differences between Validate Scope and Control Scope, their importance in project management, and how they contribute to project success.

Validate Scope:

Validate Scope is a process that occurs during the project execution phase when a deliverable is ready to be delivered. Its primary objective is to ensure that the deliverables produced during project execution meet the requirements and expectations defined in the project scope statement. The key activities involved in Validate Scope include:

Inspecting Deliverables:

Validate scope is primarily be done by a team member who was responsible for understanding and documenting the customer requirements. A Business Analyst. BA, along with key stakeholders, reviews the completed deliverables to verify if they meet the specified acceptance criteria.

Obtaining Acceptance:

The business analyst seeks formal acceptance from the stakeholders for the completed deliverables. This process involves obtaining sign-offs and documented confirmation.

Managing Change Requests:

During the Validate Scope process, any requested changes or modifications to the deliverables are documented and processed through the integrated change control system.

The importance of Validate Scope lies in ensuring that the project deliverables are correct and complete. In other words , they are of acceptable quality and align with stakeholder expectations. It helps prevent scope creep and ensures that the project remains on track.

Control Scope:

Control Scope is an ongoing process that starts during project planning and continues throughout project execution. Its primary objective is to monitor and control any changes to the project scope or deviations from it. The key activities involved in Control Scope include:

Monitoring Scope:

The project team closely monitors the project scope, including deliverables, requirements, and objectives. Any deviations or potential changes are identified and assessed.

Evaluating Change Requests:

Change requests are evaluated based on their impact on the project’s scope, schedule, budget, and overall objectives. All changes go through Change Control Process in which, the change control board reviews and approves or rejects the requests.

Managing Scope Baseline:

The project scope baseline, which includes the approved project scope statement, deliverables, and associated documentation, is updated whenever changes are approved.

Join the next PMP Exam Prep Training. Click here to learn more

The importance of Control Scope lies in maintaining project focus and preventing uncontrolled changes that can lead to scope creep. It ensures that any requested changes are evaluated, documented, and implemented in a controlled manner. Control scope ensures the sanctity of the scope baseline.

Differences between Validate Scope and Control Scope:

Timing:

Validate Scope occurs during project execution when any deliverable is ready to be delivered, while Control Scope starts during project planning and continues throughout project execution. Control Scope is generally part of weekly review.

Objective:

Validate Scope focuses on verifying if deliverables meet specified acceptance criteria, while Control Scope focuses on monitoring and controlling deviations and changes to the project scope.

Activities:

Validate Scope involves inspecting deliverables, obtaining acceptance, and managing change requests. Control Scope involves monitoring scope, evaluating change requests, and managing the scope baseline.

Conclusion:

In project management, Validate Scope and Control Scope are critical processes that contribute to the success of a project. While Validate Scope ensures that deliverables pass the acceptance criteria and stakeholder expectations, Control Scope focuses on managing and controlling deviations and changes to the project scope.

By understanding the differences between Validate Scope and Control Scope and their respective activities, project managers can effectively manage scope, minimize scope creep, and maintain project focus, ultimately leading to successful project outcomes.

How is you experience with validating scope and controlling scope. Please do share your thoughts. If you have any related questions, please post them in the comments, I will try my best to reply at the earliest.

Leave a Reply

Your email address will not be published. Required fields are marked *

pmwares is a project management consulting company enabling organizations to empower their teams and take their business to new heights.
Company

© 2024 · pmwares · All Rights Reserved · Terms & Conditions · Privacy Policy · Refund Policy